Restoration Project
of our Church continued

 

Scaffolding throughout the inside of our Church
for restoration work

 

 

 

 

 
Walls Plastered & Painted

 
Walls to be Painted

 
Wall to be painted                                       Floor half sanded

 
Floor being sanded                                 Radiators installed floor sanded

 

High Altar Restored

All Altar`s Restored

 

Screen at Back of Chrch

 

Restoration of Pews

Restoration Update of our Church

We have been praying the "Novena" in honour of the
Sacrament of the Holy Eucharist - our special request for the
successful restoration of our Church.
"Whatever you ask for in prayer and do so with faith,
you will recieve" (Mt 21.22)

We have been asking for a special favour in this Novena
"That we are successful in restoring our Parish Church,
Our Lady and St Patrick, making it a house of beauty for
the presence of the Blessed Sacrament"

Thank you for your continued prayers, support and patience,
some of us are disillutioned,upset, but we have to be strong,
we have our faith.


The Trustees of the Archdiocese have approved
an additional loan of £508,000 to complete the repairs
to the high altars, which was not included in the original
estimate of the cost of the works outstanding, which now
stands at £700.000. The Trustees have given their
commitment that the work on the restoration of the
Church will continue without any further problems and
that it will be completed in time for Easter 2009.
A full report on progress and how our Parish has the
responsibility of repaying this loan will be available shortly.


Our Lady & St Patrick's

Church Restoration Update - January'2010

Ladies and Gentlemen

On behalf of Fr John Meredith and the Finance Committee, we are pleased to present the following
update for the Church restoration:-

We have just passed our first anniversary since we moved back into Our Lady and St Patrick's following
the devastation of the Sanctuary in May 2008. Over the last eighteen months much has been achieved
    
and it is easy to recognise the beauty of our heritage.
                                                               
However, as 2009 has progressed it is clear we have not won the battle against the prevailing onslaught of
the cruel damp in the Sanctuary, above Our Lady's Altar, the Confessional and in the vicinity of the organ

loft. Indeed, the damp has contributed to further problems within the Church affecting the oak floor for
   
example. These matters and with particular attention to the damp, have been referred to the Diocesan
    
Architect. The problem areas have been inspected and corrective action has been approved by the
        
Archbishop, the Diocesan Architect and Diocesan Finance Committee. They are fully committed to
        
securing the future of Our Lady & St Patrick's and to the Parish community of Maesteg. Work will
         
commence in 2010. Father John is actively progressing this.
                                                  
Suffice to say, one can compare the progress of our Church restoration to a 'runner' that sat in many of
    
our old home passage ways. One lays it down, stands back and admires its pattern. Shortly after, it
        
moves and it forms a 'kink' over which one trips. It's pulled straight again and one is content. It kinks
      
again and yes, we trip over it yet again. Like the runner, we have and will continue to meet many
            
obstacles over which we will 'trip over' in the next few years. With your support and patience, we will
    
meet these challenges, overcome them and secure our Church for us and for future generations. So we
   
say to you our parishioners, keep vigilant and draw to the attention of Father John or any member of the
 
Finance Committee any aspect of deterioration or fabric degradation you might observe in any area of the
Church, externally and internally.
                                                                                       

        Work completed since update June 2009:-                                                                          

• Our Pascal Candle, 3 candle stands, 4 Benediction candelabras, 8 vases have been fully restored -
cost of £1426.**                                                                                               

• The sacristy, confessionals and passageway flooring between the Church and Presbytery have     
been laid with oak. A few matters are still to be addressed. The stairs leading to the organ loft  
have been restored with oak. Total cost £2900 of this work. **                                      

• The loop system was re-installed, but due to the work in the Sacristy it needs to be re-adjusted.    
This is in hand.                                                                                                 

• The Tabernacle, the home of our Blessed Lord, has been refurbished - padded and fitted with new
curtains; Confessional Box curtains replaced; main Altar under Cloth replaced; the Cedilla Chairs  
in the Sanctuary have been recovered to match and compliment the chairs in the sanctuary and the
kneelers. Total cost £260. **                                                                                  

• The entrance bell has been re-hung.                                                                          

Work in progress:-
                                                                                          

• The Cross, part of the original Church furnishings, is currently being refurbished, to return shortly.
   Apart from the Sanctuary Lamp, this will complete the restoration of the original Church brass. **

• Work shall begin soon to re-address the prevailing problem of damp within the Church fabric.   

• Sound proofing for the Confessionals is being addressed.                                               

  • The structural work for the screen is completed. It remains to have the glass panel fitted along side
the 1st War Memorial and to select images for the top glass panels to be engraved. **         

• The matter of crumbling Bath stone continues to be monitored. Recently further problems have  
been observed and have been drawn to the attention of the Architects.                            

• Church Glass of Cardiff is in the process of colour matching the damaged stained glass. The    
windows are scheduled for completion in the first quarter of 2010.                                

• A splendid job by 'Pen-y-Bont Polishers' is work in progress restoring the oak pews in their    
originalnatural colour. The work is all hand and will take 40 weeks approx to complete.Total
cost £6000.**                                                                                             

• Work has begun to recover the kneelers; the material selected is of 'heavy industrial/domestic
   
strength'. Certain issues in terms of the tight fitting between the two sets of movable kneelers in
  each row once covered has been identified and addressed by the Upholsterer. The missing     
    kneelers shall be replaced, which will be completed in line with the return of each set of restored
   pews and the benches will be placed back to their original settings. Total cost £1200.**         

• The sacristy is drawing to completion and will be fully functional by the end of January. **      

  • The old clock has been restored and hung on the balcony. The next step is to get the clockmaker
back to re-set the workings. **                                                                          

• In March, we shall have available to all our Church societies, groups and also the Primary School
a fully functional kitchen, totally independent of the Presbytery. This can be used in support of  
UCM Cream Teas, Parish & Deanery BBQs, garden parties, preparation for general fundraising
and social events. This has been totally funded by private donation. **

Next steps:-

• Redress the problem of damp and crumbling bath stone.

• Replace damaged missals and replace old vestments.
   

• Install a new Sanctuary Lamp bracket and pulley.
       

• Make provision for a new repository.
                     

            • Install additional banisters along the stairs leading to the organ loft.

• Reinstall electric bell system.                                 

Develop long term maintenance plan.                  

NB:
Please note that the bullet points suffixed by a ' double astrix -**' are not funded from the Diocesan
loan which still stands at approximately £629,000, but have been funded by monies made available by
'Private Donations and Fundraising'.
                                                                          

Acknowledgements

As we approach the close of 2009 we would like to recognise and acknowledge the contribution made by so many
in support of the restoration and enhancement of Our Lady & St Patrick's - in no particular order.
                    
Sincere and grateful thanks:
                                                                                                         

• To Fr David Smith for leading us into the commencement of the Church restoration.                          

• To Fr William Isaac for his continued support to Our Lady & St Patrick's during his administration period
and indeed prior to. For elevating developing problems to the Diocesan architects.                          

 • To the Union of Catholic Mothers who have tirelessly worked to provide fund raising to the sum of £5500.

• To the Fund Raising Group who has raised the sum of £6200 through staged events.                        

• To the Coffee Morning Group who have raised £1138.                                                            

• To the 300+ Club Members who have funded the lighting on the front steps, the protective screens        
  covering the stained glass windows, new Altar cloths, new funeral, wedding and baptism books; totalling
£4181.00. Thanks also to the 300+ Club Team for their commitment in promoting this Scheme.         

• To the Voucher Scheme team, who with Parish support, has increased the revenue considerably to £2672.

• To the Catholic Social Club Members for payment of new doors at the back of the Church totalling £2400.

• To Ann for continuing to run the Webb Ivory Promotion.                                                            

• To Doug for his tremendous work in making crosses out of our left over benches/kneelers - £1500 raised.

• To those who have made and continuing to make private donations.
                                              

• To the bereaved families who have made donations in lieu of flowers.                                             

• New Kitchen - to the Stanton family who donated both materials and labour to build and create the shell of
the new 'Parish Kitchen' and interior plastering, etc.; to Ron and Sandra Richards for donating the kitchen
units and cupboards and to Margaret and Eddie Buckley for donating the wall/ floor tiles and the cooker.

• To Linda and Steve Williams for donating the fridge/freezer.                                                       

• To Tony who has donated his time tirelessly/freely in the evenings to install and pull together the various   

elements to complete the kitchen and to make it functional ready for 2010.                                   

• To the young lads who worked so hard in the Sacristy.                                                            

• To the friends of the Restoration Fund - who purchased/donated round tables for the fundraising events.

• To each and every once of you, who have contributed to the restoration fund and Church                  
development, whether by the monthly collection plate, attending events or providing valuable time.     

THANK YOU.

Our Lady and St.Patricks Church Need your Help!

May be you have some connections with this parish and some memories of the church.  If you would like to help
with the restoration in anyway please contact the Parish Priest.

       
 
Web Site Copyright © 2007 ITCS (UK) Ltd. All rights reserved